Rebuilding A Spring Fed Pond
May 5th Pond begins with soil samples. The almost 2 acre pond will be dredged and increased to almost 3 acres. The pond is fed by a couple of strong springs that originate from a foundation of a house no longer standing on the property. The pond is the headwaters for the Honey Run Stream that flows into the Killbuck River then into the Walhounding River then followed by the Muskingum River then into the Ohio River followed by the Mississippi River. The pond will be completed by Larry Orr and his son Brian. They are hired to complete the job based on many years experience.
165
Dec 8th Spreading large pieces of shale around the pond for erosion control and discouraging Muskrats.
166
Dec 8th
167
Dec 8th Pumping out water to make sure the water does not cover where the rocks need to be placed.
168
Dec 8th.
169
Dec 8th Structure is almost gone in the shallow area
170
Dec 8th Just the top of O"Sullivan Rock is visable
159
Dec 6th Another 2" of rain really brings the pond up
160
Dec 6th Most structure covered.
161
Dec 6th Water is really muddy due to run off over stripped soil
162
Dec 6th Overflow is properly installed simple yet effective
163
Dec 6th This box goes down and meets the pipe running through the dam
164
Dec 6th A series of heavy adjustable aluminum baffles controls how high the water needs to rise before it falls over the exsisting baffles left in the hole. In this position the water would have to rise all the way to the top and the water be at its highest point the pond could hold. The tool in the well caseing is used to adjust the baffles.
157
Dec 1st Nice dry day maybe tomorrow they will be able to continue progress
158

Dec st Structure slowly sinking
153
Nov 30th Another 4" deeper
154
Nov 30th Nice dry days ahead
155
Nov 30th About 6ft until full pool
156
Nov 30th Whats left not filled will less then 6ft deep
145
Nov 29th 3" of rain and things happen quickly
146
Nov 29th All I can say is wow!
147
Nov 29th Pond needs only 6ft to be at full pool
148
Nov 29th Could be the last time you see the point
149
Nov 29th Will not last long
152

Nov 29th Contrast
150
Nov 29th The deepest water in the pond is already 7ft
151
Nov 29th Last sit on the rock pile
141
Nov 27th After around .5 inches of rain the spring is in high gear
142
Nov 27th Sloppy
143
Nov 27th
144
Nov 27th Some structure start to get covered
Pond is offically filling
Pond is offically filling
136
Nov 26th Getting closer to done with the dam
137
Nov 26th Water starts to fill the pond.
138
Nov 26th Very exciting
139
Nov 26th Placing the last marker buoy the end has a stainless ring on it to anchor my small
140
Nov 26th Placing the rocks I brought back with me from Northern Canada hoping that some day the fishing is as good as O'sullivans Rainbow Lodge near Nakina Ontario
134
Nov 25th Starting on closing the dam for water retaining
135
Nov 25th Packing the clay.

Nov 20th Setting the last few pieces of structure
121

Nov 19th Pond is neary finished with shaping
122

Nov 19th Some depths perspective
123

Nov 19th The point and rock piles
124

Nov 19th Garrett and Grandpa grab some more rocks for the pond
125
Nov 19th Pauls handling of tractor is percise
126

Nov 19th Paul decides to help Larry with some dirt moving
127
Nov 19th Nice rigs
128
Nov 19th Paul backs out over the point
!29
Nov 19th Jenny wants to know where I want this piece of structure
130
Nov 19th Getting some air
131
Nov 18th rerouting the spring feed
!32
Nov 18th Ready to cut the new feed
133
Nov 18th Digging hard and fast in good weather
119
Nov17th Pond building continues after 2 day rain
120
Nov 17th
117
Nov 15th The Point continues to get more rocks
118
Nov 15th Bluegill deep structure for ice-fishing about 12ft deep
107
Nov 12th Skidsteer arrives
108
Nov 12th
109
Nov 12th Garrett dumps more rock structure
110
Nov 12th about 4 loads
111
Nov 12th This is when things go wrong. They were burning a pile of stumps and the wind really took off. The sparks carried about 100ft over bare land and started the woods on FIRE
112
Nov 12th We put it out by working hard and fast. The leaves were really dry and the smoke made it hard to breath. But we worked togeather and stopped the flames.
113
Nov 12th The problem was there were alot of fallen dead trees that caught on fire and wouldn't go out
114

Nov 12th You guessed it America's best were called.
115
Nov 12th We called them to make sure this thing would not catch fire again with a cornfield in the not so distant dirction of the wind we did not want to take any chances it was about half an acre that burned.
116
Nov 12th Larry startes the liner and shale that will surround the pond.
101
Nov 11th Big dozier moved
102
Nov 11th Bigger hoe also moved in
103
Nov 11th Structure on the point complete
104
Nov11th Starting to place rock structure near BG spawning grounds
105
Nov 11th Really cool 1971 Ford Cab-over
106

Nov 11th The rear has been replaced with Mack air ride instead of the orginal springs
96

Nov 10th Rain holds off again
97
Nov 10th Continueing on the core construction
98
Nov 10th Pond will be deep
99
Nov 10th Adding more structure to my yet unnamed point
100
Nov 10th Note marker buoy it is placed near the rock pile so that the point will be clearly found from the dock on one side and the flat casting rock built on the other. I put a small stainless ring on the end of the buoy to anchor the boat over the rock pile
93

Nov 8th Diggin hard
94

Nov 8th Placed the big rocks just at the end of the point
95
Nov 8th Plan to make a bunch of small piles up on the top of the point and increasing the large one
91
Nov 7th Driving the tractor back to the pond to do some work
90
Nov 7th Pushed rocks into the pond where Brian Orr will place them with the hoe on the point.
92
Nov 7th Placed some structure tonight. The rocks to be added to the end of the point are in the back ground
83
Nov 5th Construction complete on the mini point it runs about 100ft off the dam with a sharp drop off on one side and a gentle slope on the other. Note the nice shadow created by the point.
84
Nov 5th Sharp drop side
85
Nov 5th Slow tapering side
86
Nov 5th The point starts in about 11ft comes up to about 5ft and then back to 12ft
87
Nov 5th
88
Nov 5th Hoe master
89
Nov 5th Garrett Kurtz Excavating at your service
82
Nov 3rd The pond dries out enough to continue
81
Nov 3rd Pins indicate new section to be dug
80
Nov 3rd Dam core packed tightly
79
Oct 25th Days are getting shorter
801
This is what they call the dam core its where the dam will be in the new addition to the pond
81
Oct 25th Packer
82
Oct 25th Laying the pipe leaving the over flow
78
Oct 24th Path to pond
77
Oct 24th Path to pond
76
Oct 24th Peak leaves
79
Oct 24th Water flowing
75
Oct 24th Water flowing into pond
80
Oct 24th Wet pond
Oct 18th-19th Soggy cold rain. We are located just above the 'N' in New Philadelphia
Oct 18th-19th Soggy cold rain. We are located just above the 'N' in New Philadelphia
74

Oct 18 Last nice day for awhile
75
Oct 18th Second spawning area
76
Oct 18th Depth around pond
77
Oct 18th Deepest area is about 12ft
71
Oct 17th Leaves took hit from 45 mph wind gusts
72
Oct 17th Holmes County's rolling hills
73

Oct 17th Beginning to see our house with the leaves thinning out
70
Oct 17th found tile with water flowing fast below water line
69
Found spring culvert around water level
68
Oct 17th Solid flow
67

Oct 15th Placing the first cover
68
Oct 15th Need to bury them into the ground to secure them
69

Oct 15th Old farm equipment near the old foundation
70
Oct 15th DUNHAM 8' CULTIPACKER
66
Oct 11th Here is an old foundation located near the pond where we are getting our sandstone for rock piles and support for the flat rocks placed just off the shore around the pond for casting platforms. This old house was moved in the late 40's because of its lack of access. Cars would have had a difficult time getting down the old drive. The place is a little creepy. We would love to clean it up getting rid of the briars and imagine life of old. There are a bunch of old farming equipment around and a spring sistern we have not located yet. It would be fun to have a metal detector back here.
65
Oct 11th Sand stone foundation with trees growing out of it.
64
Oct 11th Paul pulls out sandstone beween trees where house was moved in the late 40's
63
Oct 11th Plenty of these for structure
62
Oct 11th Spawning area there will be another larger area not yet constructed
61
Oct11th Another view of spawning area
59
Oct 11th Shaping the shore
57
58
Oct 10th 7 days with no rain very helpful
Oct 10th Leaves are changing
56
Oct10th
55
Oct 10th These are the rocks to be placed as casting platforms they are flat on the bottom. These will be casting distance of my structure
54
Oct 10th Brought these rocks in with the trailer very heavy took my time they are flat on one side and will be used to step out on to fish
55
Oct 10th Yes sir
53
Oct 10th working on the sides
51
Checking elevation
50
Oct 9th
49
Oct 8th Loading firewood
48
Oct 8th
47
46
A little soft though
45
Marsh area passable
44
43
43
Garrett loves construction stuff
42
Muck is starting to fill swale
41
Hills of Holmes County
40
Oct 6th leaves just starting
39
Shale base
38
Driveway is very solid
37
Oct 6th Another perfect day
35
33
Larry is an operator not just someone who can run a hoe
32
Oct 4th Loading the muck
31
Oct 3 Piling the muck
30
Sept 29th progress rain tomorrow
29
Big snapper
28
Gooy muck
27
Loading the truck
26
Long reach
25
Sept 28th Starting the process of removing the muck
Drying out the marsh area on the south side of the pond with french style drain
24
4th wettest year with 3 months to go
23
Next week is hopefully dryer
22
Sept 27th Tiling the marshy section to get the dump trucks through
19
Spring still pushes water through pond.
18
Thursday Sept 22 removed the willows at the end of the pond everything is very wet
17
Another trackhoe brought in still to wet Tuesday September 20
16
Note mud getting worse it will take some dry weather to dry this thing hopefully October will bring some nice days
15
Moving in some shale to improve the drive way
14
Checking out the grade
12
Pushing off the top of the marshy area so that they can tile it to get dump trucks across
11
Dozier removed all fence posts and a few trees to make room for dump trucks
13
Small dozier arrives
10

Map of area to be enlarged. Pond will be around 3 acres give or take
9

The boy helps
8
Bass of any size can't get around in there.
7
This is a bluegil safety area will have 3 of these
6
Building structure for the pond. Made 6 of these today. moss will cover the pvc pipe making cover that won't go away.
5
First they will tile one end of the pond that is really marsh like due to that spring entering that cornor. They need to be able to drive their dump trucks through there.
4
Its been raining every day for a week due to Tropical Storm Lee sitting here spinning its little thunder storm gifts a couple times a day
3
They moved this in Sept 9th the web site says it can reach 47ft down thats deep. http://www.lbxco.com/Specs/3400_LF211.pdf
2
First piece of equipment moves in Sept 5th
Dam was in bad shape if not for large springs entering the pond it would have been really low
1
Drained summer of 2011 2 acres is the present size. It was built about 40 years ago. It was built before no-till farming was introduced and has massive silt from run off after spring plowing. Max depth was 8ft most was 4ft. These springs that feed the pond overflow and forms the Honeyrun Creek headwaters. From here it flows to the Killbuck River then into the Walhounding River then the Muskingum River then into the Ohio River then finally the Mississippi River.